WAPDA Initiates Emergency Dewatering at Tarbela T-5 Following Tunnel Inundation

Hydroelectric authority mobilises high-capacity pumps and concrete plugging operations after weak rock mass collapse breaches intake pit during extension excavation.

PNA Energy & Water Desk
Islamabad Bureau
Pakistan News AgencyArchival Image

The Pakistan Water and Power Development Authority (WAPDA) has commenced round-the-clock dewatering operations and structural remediation at the Tarbela Dam 5th Extension (T-5) Hydropower Project, following an accidental inundation triggered by the localized collapse of a weak rock mass during excavation work.

According to technical briefings from project engineers, the incident occurred during the construction of the second bench of the connecting tunnel, when unstable subterranean rock adjacent to the intake pit breached under hydraulic pressure, allowing water to flow into Tunnel 5 and the under-construction powerhouse basin. Project safety teams immediately executed emergency evacuation procedures, safely extricating all domestic and international personnel from the subterranean work zones without fatalities.

WAPDA clarified that core structural elements—including the main Tarbela earthen dam, the operational reservoir spillways, the completed power tunnel, and the high-voltage switchyard—remain completely undamaged and intact. High-capacity industrial drainage pumps were deployed to clear accumulated water from the powerhouse basin, while specialized civil engineering teams began pumping concrete to permanently seal the geological breach.

Construction operations on the affected tunnel segment have been temporarily paused while national and international geotechnical consultants conduct exhaustive structural stability surveys. Energy authorities confirmed that water storage and routine irrigation releases through Tarbela Dam continue strictly as scheduled under Indus River System Authority (IRSA) operational quotas.

Related Topics
#Tarbela Dam#WAPDA#Hydropower#Water Resources#Infrastructure#Engineering

Source: Filed by PNA Energy & Water Desk for the Pakistan News Agency. Distributed under national news syndication standards.